The City of Auburn is issuing a Notice of Application (NOA) and Determination of Non-Significance (DNS) for the following described project. 

Proposal: The removal and replacement of over 30,000 square feet (SF) of failing pavement located on the west side of Building 17-07 and at the 5-way intersection between Building 17-66 and 17-68, and revisions to the existing storm drainage system. 

Location: The project is located at 700 15th St. SW within SE ¼ of Section 25, Township 21, Range 04, on a portion of the existing Boeing Auburn facility, south of 15th St. SW between Perimeter Rd. SW and Pacific Ave. S, on Parcel No. 2521049107 and along East Blvd. (internal street on the Boeing campus) on Parcel No. 2521049105.

Notice of Application:
November 13, 2019
Notice of Complete
July 29, 2019
Permit Application:
July 9, 2019

File No. 
SEP19-0023

Applicant/Property Owner:
Katrina Toole, Project Administrator/Permit Focal
The Boeing Company, Site Services
P.O. Box 3707 MC 5C-210
Seattle, WA 98124

Studies/Plans Submitted with Application:
Revised SEPA Checklist (PDF), The Boeing Company, dated 10/28/19
Grading Plans (PDF), Sitts & Hill Engineers, Inc., dated 11/4/19
Geotechnical Engineering Report (PDF), Migizi Group, Inc., dated 3/17/16
Stormwater Site Plan (PDF), Sitts & Hill Engineers, Inc., dated 8/7/19
Construction Stormwater Pollution Prevention Plan (PDF), Sitts & Hill Engineers, Inc., dated 8/7/19
 
Other Permits, Plans, and Approvals Needed:
City of Auburn Grading Permit (GRA19-0029)
City of Auburn Level 2 Storm Permit

Statement of Consistency and List of Applicable Development Regulations:  This proposal is subject to and shall be consistent with the Auburn City Code, Comprehensive Plan, and Public Works Design and Construction Standards.

Lead Agency: City of Auburn

The lead agency for this proposal has determined that it does not have probable significant adverse impact on the environment. An environmental impact statement (EIS) is not required under RCW 43.21C.030(2)(c). This decision was made after review of a completed environmental checklist and other information on file with the lead agency. This information is available to the public on request. 

Public Comment Period: This may be your only opportunity to comment on the environmental impact of the proposal. All persons may comment on this application. This DNS is issued under WAC 197-11-340(2); the lead agency will not act on this proposal for 15 days from the date issued below. Comments must be in writing and submitted by 5:00 PM on December 2, 2019 o the mailing address of 25 W Main St., Auburn, WA, 98001 or to the email address below. Any person wishing to become a party of record, shall include in their comments that they wish to receive notice of and participate in any hearings, if relevant, and request a copy of decisions once made. Any person aggrieved of the City's determination may file an appeal with the Auburn City Clerk at 25 W Main St., Auburn, WA 98001-4998 within 14 days of the close of the comment period, or by 5:00 PM on December 16, 2019.

Public Hearing: A public hearing is not required for this proposal. 

Note: This determination does not constitute approval of the proposal. Approval of the proposal can only be made by the legislative or administrative body vested with that authority. The proposal is required to meet all applicable regulations.