Administrative Use Permit Accessory Building Height

NOTICE OF APPLICATION (NOA)
ADMINISTRATIVE VARIANCE USE PERMIT
ACCESSORY (GARAGE) BUILDING HEIGHT
VAR25-0011

The City of Auburn is issuing a Notice of Application (NOA) for the following described project. The permit applications and listed studies may be reviewed at the Auburn Department of Community Development at One E Main St., 2nd Floor, Customer Service Center, Auburn, WA 98001 and by visiting www.auburnwa.gov/landuse.

Proposal: Construction of 1,995 square foot shop/garage building in the R-2 Residential Low Zone and Lea Hill Overlay. The current height for accessory structures in the Lea Hill Overlay R-2 is 16 feet. The Administrative Variance to building height will increase the accessory structure’s (shop/garage) height by approximately 45.6% of the quantifiable standard (from 16 feet to 23.3 feet).

Location: The site is located north of the intersection of 105th Ave. NW and 281st St. SE, addressed as 28008 105th Ave. SE, King Co. Parcel No. 3222059117.

Notice of Application:      
December 30, 2025

Application Complete:  
December 9, 2025

Permit Application:          
December 1, 2025

Application File No.     
VAR25-0011

Applicant:   
Viktor Roshchuk
1505 68th St. SE
Auburn, WA 98092

Property Owner:     
Babshinskiy Angelina Viktor
28008 105th Ave. SE
Auburn, WA 98092

Studies/Plans Submitted With Application:
Site Plan (PDF), prepared by VNR Design, dated November 4, 2025
Building Elevations (PDF), prepared by VNR Design, dated November 4, 2025
Building Floor Plans (PDF), prepared by VNR Design, dated November 4, 2025

Other Permits, Plans, and Approvals Needed:
Building Permit

Statement of Consistency and List of Applicable Development Regulations:  This proposal is subject to and shall be consistent with the Auburn City Code, Comprehensive Plan, and Public Works Design and Construction Standards.

Public Comment Period: All persons may comment on this application. Comments must be in writing and submitted by 5:00 PM on January 14, 2026, to the mailing address of 25 W Main St., Auburn, WA, 98001 or emailed to the contact below. Any person wishing to become a party of record, shall include in their comments that they wish to receive notice of and participate in any hearings, if relevant, request a copy of decisions once made, and be made aware of appeal rights. For questions regarding this project, please contact Muwaffaq Usman Adam, PMP, AICP, Planner I at [email protected]or 253-398-7353.

VICINITY MAP

Vicinity Map VAR25-0011

SITE PLAN

SITE PLAN - VAR25-0011